A Texas-based company that wanted to put wind turbines along Shinbone Ridge
in Etowah and Cherokee County, has abandoned the project because the
restrictions imposed by Alabama legislation passed in the last session were
“just too restrictive.” Attorney Charles
Stewart, representing Pioneer Green, said the project has been canceled in both
Etowah and Cherokee counties because of legislation passed establishing parameters for any wind
turbine project, including setback lines and permitting through the Public
Service Commission, Pioneer Green had to reevaluate the project.Thursday, August 21, 2014
Company abandons wind farm projects in Etowah and Cherokee counties
A Texas-based company that wanted to put wind turbines along Shinbone Ridge
in Etowah and Cherokee County, has abandoned the project because the
restrictions imposed by Alabama legislation passed in the last session were
“just too restrictive.” Attorney Charles
Stewart, representing Pioneer Green, said the project has been canceled in both
Etowah and Cherokee counties because of legislation passed establishing parameters for any wind
turbine project, including setback lines and permitting through the Public
Service Commission, Pioneer Green had to reevaluate the project.